Savannah Arts Academy

The Savannah Arts Academy Addition and Renovation included phased demolition, a large addition, and renovation of the historic school while the campus remained occupied.

Project Highlight

Renovating a Savannah's Historic School While it is Occupied: The Savannah Arts Academy project involved a complex, multi-phased renovation of a 1937 historic school campus, while occupied. The scope included comprehensive classroom upgrades, restoration of the historic auditorium, mechanical and fire alarm system replacements, enhanced security measures, and a new cafeteria.

Challenge

Renovating the mechanical systems in a historic building presented significant challenges, particularly because the existing equipment was outdated and the mechanical rooms were undersized. Simultaneous work across multiple areas required precise coordination to avoid disrupting school operations.

Solution

McKnight Construction developed an innovative approach to replace the mechanical systems without reconstructing the mechanical rooms. By carefully coordinating equipment deliveries and utilizing compact, high-efficiency units, McKnight minimized downtime and maintained the integrity of the historic structure, ensuring the school remained functional throughout the renovation.

0+
Yes
Square Feet
0+
15000
New Additions
0+
LWMBE Participation (%)
{
"McKnight Construction exhibited an impressive level of professionalism and expertise in navigating the challenges posed by the building's historic significance. Their commitment to preserving the integrity of the landmark while enhancing its functionality reflects a level of dedication rarely seen in the construction industry."
- David A. Duvall
Senior Construction Manager Savannah Chatham Co Public School System